Takt time is the pace a lean process has to keep: the time available divided by what the customer needs. Enter your shift pattern and daily demand, and add your total work content to see how many operators the line needs.

Takt time

60 sec

One finished unit every 1 minute meets demand.

Available time per day
880 min
Units per hour needed
60
Operators needed
4 → staff 4
Your line against taktWork content split evenly across the stations you would staff.
Takt 60 s
Stn 1Stn 2Stn 3Stn 4

4 stations at 60 s of work each, 100% of takt. Real stations are rarely this even, so check each one against the line.

Example values are filled in. Replace them with your own; nothing you type leaves your browser.

Worked example

The example values, step by step

  1. Step 1 · Time per shift

    480 min − 40 min breaks

    = 440 min

  2. Step 2 · Available time

    440 min × 2 shifts

    = 880 min a day

  3. Step 3 · Takt time

    880 min ÷ 880 units

    = 1 min (60 s)

  4. Step 4 · Operators needed

    240 s work content ÷ 60 s

    = 4 operators

Reading the result

In the example, the line must finish one unit every minute to meet demand. With 240 seconds of manual work per unit, that needs four balanced stations of about 60 seconds each.

If a station's cycle time is above takt, it will fall behind demand. Move work from it to stations with spare time, then update standard work.

Common data mistakes

  • Using total shift time without taking off breaks and planned stops.
  • Using a forecast that is far from actual demand, so takt is wrong from the start.
  • Treating takt as a target for how fast people should work, rather than the pace demand sets.

The formula

How it's calculated

Available time
(Shift length − Breaks) × Shifts per day
Takt time
Available time ÷ Customer demand
Operators needed
Total work content ÷ Takt time

Takt is set by the customer

Takt time is the pace you need to work at to meet demand, which can differ from the pace you are able to work at. If demand changes, takt changes with it.

Plan below takt

Few processes run perfectly. Many teams aim for station cycle times a little below takt so small problems do not stop the line from meeting demand.

Use it to balance the line

Compare each station's work content with takt on a yamazumi chart. Stations above takt are bottlenecks; stations well below it are where to move work from.

Frequently asked questions

Is takt time the same as cycle time?
No. Takt time is the required pace set by demand. Cycle time is how long the process actually takes. Cycle time should be at or below takt time.
Should I include breaks in available time?
Subtract breaks, meetings and other planned stops when the line is not producing. Do not subtract unplanned downtime. It is a problem to solve, so it does not belong in the planned allowance.
Why round operators up?
You cannot staff a fraction of a person. The gap between the exact figure and the rounded-up figure shows how much waiting or imbalance to expect.
What is the takt time formula?
Takt time equals net available production time divided by customer demand for the same period, for example 27,000 seconds ÷ 450 units = 60 seconds per unit.
What if cycle time is longer than takt?
That step cannot keep up with demand. Remove waste from it, move work to other stations, add capacity, or review the demand assumption.
Does takt time apply to services?
Yes, wherever similar work items arrive at a steady rate, such as claims or orders. Very varied, one-off work is harder to pace with takt.