Little's Law Calculator
Little's Law links three flow metrics: work in progress, throughput and cycle time. Enter any two and the calculator finds the third, then shows what happens to cycle time if you cut work in progress.
Average cycle time
5 weeks
That is about 25 working days per item.
What if we cut WIP by 50%?
WIP30 → 15 items
Cycle time5 → 2.5 weeks
Assumes throughput stays the same.
Now
5 weeks30 items
WIP cut 50%
2.5 weeks15 items
Example values are filled in. Replace them with your own; nothing you type leaves your browser.
Worked example
The example values, step by step
- Step 1 · Work in progress
Items started but not finished
= 30 items
- Step 2 · Throughput
Items finished per week
= 6 a week
- Step 3 · Average cycle time
30 ÷ 6
= 5 weeks
Reading the result
In the example, an item started today will take about five weeks to finish on average. At a five-day working week, that is about 25 working days.
If throughput holds, cutting work in progress to 15 items would halve average cycle time to about two and a half weeks. In practice the effect is smaller if the system is unstable.
Common data mistakes
- Mixing time units, such as throughput per week with cycle time in days.
- Using a one-day snapshot of WIP instead of an average over the period.
- Applying the law to a system that is growing or shrinking fast, where its averages do not hold.
The methods behind the number
The formula
How it's calculated
- Cycle time
- Work in progress ÷ Throughput
- Work in progress
- Throughput × Cycle time
- Throughput
- Work in progress ÷ Cycle time
Why limiting WIP works
If throughput stays the same, halving work in progress halves the average cycle time. That is the arithmetic behind WIP limits on a kanban board.
Use consistent units
If throughput is items per week, cycle time comes out in weeks. Mixing days and weeks is the most common mistake.
It works on averages
Little's Law describes long-run averages in a reasonably stable system. Use it to understand the system and set policies. It cannot give a reliable date for a single item.
Frequently asked questions
Does Little's Law apply to software teams?
What if our system is not stable?
How do I forecast a single item?
What is the Little's Law formula?
When does Little's Law hold?
Can I use Little's Law to set WIP limits?
Sources and further reading
- John D. C. Little, "A Proof for the Queuing Formula: L = λW", Operations Research, 1961 (article)
- The Kanban Guide (Vacanti and Coleman) ↗
For vendors
Built a lean tool?
Submit it for review. Every tool is checked against our listing criteria and researched from public sources. Approved tools join their category in the next published batch.