To measure OEE, record planned time, downtime, total count and good count for one machine on every shift.
Overall equipment effectiveness multiplies availability, performance and quality into one number. The number matters less than the losses behind it.
You can start measuring OEE this week with a sheet of paper. This guide explains the formula, what to record and when software starts to help.
How to calculate OEE
Availability is run time divided by planned production time. Performance is ideal cycle time times total count, divided by run time. Quality is good count divided by total count.
OEE is the three multiplied together. The OEE calculator does the math and walks through an example step by step.
The six major losses
OEE is usually analyzed through six major losses: failures, adjustments, minor stoppages, reduced speed, scrap and rework. Seiichi Nakajima described them in his work on TPM.
Each factor of OEE holds two of the losses. Knowing which loss is largest tells you which lean tool to use next.
Start with one constraint
Measure the bottleneck machine first. It sets the output of the whole line, so gains elsewhere may not raise output.
An OEE tracking sheet on paper
Put a sheet at the machine with one row per hour. Operators record the planned output, the actual output, stops longer than a few minutes and a reason code for each.
Keep the reason codes short and agreed with the team, such as no material, changeover, breakdown and quality check. Review the sheet at the daily huddle.
Make losses visible
Show the loss Pareto at the shift huddle, so the team can act on it. Andon signals help the team react while the loss is happening, not the next day.
Setup losses point to SMED. Breakdowns and minor stops point to TPM.
When to automate OEE tracking
Manual sheets catch long stops well but miss minor stops and slow running. Move to OEE software when those losses matter, or when you track more than a few machines.
The lean manufacturing guide shows how OEE fits with the other shop-floor tools.
Frequently asked questions
How is OEE calculated?
What are the six big losses in OEE?
Do you need software to start measuring OEE?
Which machine should you measure first?